Nearly there now …
Here’s a design layout to show what the front of the new unit will look like when it is finished. You can see on the top of the right-hand window our new 01392 ‘local’ telephone number and the lovely clean lines of our frontage will demonstrate the care we take in looking after your ears!
As you can see, the builders have nearly finished the setting out work in our new unit. In the picture on the left you can see all the walls in place for our new clinic rooms. All the power and lighting currently has to be run on builder’s jury rigs from the main board as the new fitting are not yet wired.
Here, on the right, is the inside of one of the treatment rooms after the second electrical fit. Once the walls are painted, the light and power fittings will be pushed into place and safely secured.
At the front of the unit you can see the door-frame for the right hand treatment room has been fitted, while the left still remains to be added. Builders seem to make a lot of mess, but this will all soon be cleared away and look amazing.
This weekend should see all the painting being done and the flooring being laid. The transformation is almost complete. We are running a couple of days behind schedule, but hope to be moving in on Wednesday. Come on down and have a look. Do pop in and say hello, we’d love to see you and show you around.